The mill engaged USC Consulting Group to create and execute an integrated master plan, and ensure that all parties involved – internal and external were ready to execute their portions of the mill upgrade installation. Known for its fact-based, action-driven, hands-on approach to solution implementation, USC quickly assessed the situation and deployed functional teams aligned along installation areas as well a management oversight team to facilitate team readiness. Extensive checklists were developed by which the teams had to prove their readiness, actions identified and taken.
USC Consulting Group was brought in to orchestrate the creation of an integrated project schedule using critical path methods, and to monitor the outage execution. To facilitate outage readiness, oversight teams were deployed for the installation areas to validate what was complete and ready, and what was required to complete. Utilizing extensive checklists, action item lists, and regular meetings with the management team, the oversight teams had to prove their readiness for outage planning, execution and production. USC facilitated the meetings and followed up on action items with the teams.
The nucleus of this engagement was USC’s Outage Management Methodology that focuses on Critical Path Methods, employee engagement, and action-driven follow-up for planning and schedule development. The integrated project schedule was developed through the engagement of project engineers and contractors to construct precedence networks via interactive whiteboard sessions. In these sessions, USC facilitated the creation of the optimal sequence of flow, resources required, expected task durations and any additional task attributes such as special equipment and contractor performing the work. These networks were entered into a project planning tool and sequenced together from which a critical path was created.
Outage execution was monitored by developing custom reports in the project planning tool, based on filtering and sorting by the task attributes. The reports were followed up during outage shifts by collecting task-level percent of completion and actual durations then updating the planning tool. New reports were provided to the next outage shift for follow-up. A key element of the plant-wide shift review meetings was the need to have a visual reference from which to mark progress and provide a focal point of discussion in the event issues arose. To provide that visual reference, the precedence networks were printed on large format plotters, activities marked off when completed and notes made on the plots where issues arose and mitigated.