Nationwide wastewater services provider, Energy & Utilities case study

Case study · Energy & Utilities

Wastewater contractor raises sewer cleaning from 700 to 1,800 feet per truck a day

Three quarters through the year, a wastewater services provider had cleaned less than 60% of the sewer footage its city contract required. USC rebalanced crews, trucks and daily work plans, and the provider hit its annual goal before Christmas.

Results

1,800

feet of pipe per truck per day, up from 700

65,000

feet of pipe a week, up from 13,000

90%+

equipment utilization, up from the mid-60s

The provider reached its annual footage goal before Christmas.

The situation

The provider had to clean, inspect, test and repair more than 2.6 million feet of sewer pipe a year for a major Midwestern city. Three quarters through the year, it had not reached 60% of its contracted footage, after a similar shortfall the year before.

What the assessment found

  • Under 60% of contract footage with a quarter left
  • Crew assignments out of balance between operators and laborers
  • Trucks split evenly, idling equipment the cleaning crews needed
  • Crews building their own daily work plans

How the work was done

Crewing: match people to work

Set expectations per task, built a resource capacity plan, added two temporary laborers and six Saturdays, and used geographic information system (GIS) data to target low-debris segments due for cleaning.

Trucks: schedule by availability

Added a fleet availability matrix so supervisors assigned trucks to available labor, and paired experienced operators with older equipment.

90%+

equipment utilization, up from the mid-60s

Jobs: plan the day centrally

Moved daily work planning to supervisors, factoring in contract priorities, work area groupings and travel time.

1,800

feet per truck per day, up from 700

Before and after

Feet of pipe per truck per day

Before: 700
After: 1,800

+157%

Feet of pipe per week

Before: 13,000
After: 65,000

+400%

Average output before and after the changes.

Lasting impact

The provider reached its annual footage goal before Christmas, avoided costly contract fines, and went into the next year with a process and plan to meet its goals.

Related case studies

Three quarters through the year and behind on the contract?