
Case study · Energy & Utilities
Wastewater contractor raises sewer cleaning from 700 to 1,800 feet per truck a day
Three quarters through the year, a wastewater services provider had cleaned less than 60% of the sewer footage its city contract required. USC rebalanced crews, trucks and daily work plans, and the provider hit its annual goal before Christmas.
Results
1,800
feet of pipe per truck per day, up from 700
65,000
feet of pipe a week, up from 13,000
90%+
equipment utilization, up from the mid-60s
The provider reached its annual footage goal before Christmas.
The situation
The provider had to clean, inspect, test and repair more than 2.6 million feet of sewer pipe a year for a major Midwestern city. Three quarters through the year, it had not reached 60% of its contracted footage, after a similar shortfall the year before.
What the assessment found
- Under 60% of contract footage with a quarter left
- Crew assignments out of balance between operators and laborers
- Trucks split evenly, idling equipment the cleaning crews needed
- Crews building their own daily work plans
How the work was done
Crewing: match people to work
Set expectations per task, built a resource capacity plan, added two temporary laborers and six Saturdays, and used geographic information system (GIS) data to target low-debris segments due for cleaning.
Trucks: schedule by availability
Added a fleet availability matrix so supervisors assigned trucks to available labor, and paired experienced operators with older equipment.
90%+
equipment utilization, up from the mid-60s
Jobs: plan the day centrally
Moved daily work planning to supervisors, factoring in contract priorities, work area groupings and travel time.
1,800
feet per truck per day, up from 700
Before and after
Feet of pipe per truck per day
+157%
Feet of pipe per week
+400%
Average output before and after the changes.
Lasting impact
The provider reached its annual footage goal before Christmas, avoided costly contract fines, and went into the next year with a process and plan to meet its goals.
Related case studies
Energy & Utilities
Midstream oil and gas company cuts $15.2M in expenses after rapid acquisitions
$15.2Min total expense reductions
Read the case study →Energy & Utilities
Waste-to-energy producer saves $3M a year by cutting overtime across U.S. plants
$3Min annual overtime savings
Read the case study →Energy & Utilities
Energy equipment maker delivers an $18.4M turnaround and doubles productivity
$18.4Mturnaround, reaching break-even against budget
Read the case study →