Auto parts maker cuts its engineering backlog 4,200 hours and clears five-day work-in-process stacks
Sales at a drivetrain and braking components maker were growing 25% a year, and large inventories were masking an inflexible production line. USC prototyped faster processes with welders and assembly teams and cleared the engineering backlog.
Results
4,200 hours
reduction in engineering backlog, from 12,000
80%
reduction in work-in-process (WIP) inventory, freeing working capital
96%
weekly engineering plan attainment, up from 44%
Five-day WIP stacks were cleared from the floor.
The situation
Sales were growing 25% a year and customers wanted faster turnaround, but the linear production process couldn't flex, so the company carried large, costly inventories.
What the assessment found
- Engineering backlog of 12,000 man-hours, with one person holding 56% of it
- Preventive maintenance backlog over 2,700 man-hours and growing
- Welding area a major bottleneck
- Five-day WIP inventories stacked 20 feet high
How the work was done
Welding: prototype a faster flow
Reworked space and flow with welders and supervisors; three weeks later the welding area outpaced the assembly lines.
Assembly: build cells
Introduced a cellular layout, kanban, quality at the source and quick changeover on both assembly lines, eliminating five-day WIP inventories.
80%
reduction in WIP inventory
Engineering: balance the backlog
Removed non-value-added and obsolete tasks, rebalanced workloads and built a simple computer-based system to plan and finish work on time.
4,200 hours
reduction in engineering backlog
Before and after
Weekly engineering plan attainment
+52 pts
Weekly attainment to the engineering plan.
Lasting impact
A state-of-the-art production cell replaced a crowded sub-assembly area, and planning discipline and metrics gave the company control of its process as demand kept climbing.