1Challenge
The mill could make 36 heats a day, but its strategy ran only two strands at once, alternating between the slab caster and the DSPC.
2Approach
- Aligned ladle steel production with sales and operations for a repeatable process
- Created contingency plans for steel in queue to absorb unplanned caster delays
- Moved to three-strand casting for constant flow and no changeover downtime
3Results
$35M
Value of implemented improvements
40%
Less in-process slab inventory
45%
Smaller steelmaking backlog
7%
Throughput increase
Cross-training and better equipment use cut crew sizes and saved capital.