1Challenge
Maintenance was being centralized, but hangar supervisors still worked reactively. Weak production control, no long-term planning and base-to-base conflicts caused material shortages.
2Approach
- Mapped planning, 24/7 hangar execution and material logistics to find and rank process gaps
- Ran joint USC–client teams on 11 key areas using project charters and kaizen
- Set baseline KPIs and tested each solution in the hangar before rollout
3Results
90%
Reduction in penalties
85%
Reduction in buy-backs
6%
Better aircraft availability and dispatch reliability
40%
Better weekend cycle-time attainment
Customers who usually called to complain called to note the improvement.
Want results like these?
Find out where your operation's biggest opportunities are.
Start with an Assessment© USC Consulting Group 2026 | Aerospace & Manufacturing. Representative industry image. Results are engagement-specific; sizing and forecast figures are labeled as such.