1Challenge
Sub-assemblies built in the trailer plant caused priority conflicts and schedule instability, quality defects added WIP, and the baseline data was unreliable.
2Approach
- Set up heijunka boards across sub-assemblies to create a traceable pull system
- Built an area readiness tracker and a standard leadership agenda to flag risks early
- Added completion checklists, quality checks and standard work to cut rework
3Results
118%
Throughput increase (11 to 24 units/week)
71%
WIP reduction (131 to 38 units)
83%
MOS audit compliance
Fewer labor hours per invoiceable unit, driven by quality and scheduling gains.