Representative illustration: A copper smelter in Southern Africa could not consistently meet its daily blister copper target.

Case Study · Mining & Metals

A copper smelter in Southern Africa could not consistently meet its daily blister copper target.

← All case studies

1Challenge

Five charges a day was a good day; six was always out of reach. No formal schedule existed, and poor communication left molten copper cooling in the aisle.

2Approach

  • Built a 'perfect day' schedule with plant managers, timing every task and enforcing it
  • Improved coordination of ladle movement between the Ausmelt and converters
  • Added pre-start checklists, a KPI database and weekly action-item management

3Results

25%

Increase in blister copper production

+139 t

Copper smelted per day

27,000 t

Reduction in reverts after 11 months

Hit the six-charge target, occasionally seven, and adopted a continuous improvement mindset.