1Challenge
Entering the automotive market required new finishing, automation and lifting equipment. Many vendors, contractors and sub-contractors had to share space, safety and utility takeover points, and the plant was not ready.
2Approach
- Built an integrated, critical-path master schedule from precedence networks developed in whiteboard sessions
- Deployed oversight teams by installation area to prove readiness with checklists and action items
- Monitored execution shift by shift with custom reports and large-format network plots
3Results
$400M
Mill upgrade program
<100
Days to outage start at engagement
On / ahead
Of schedule where the method was used
Where USC's outage methodology was adopted, work finished on or ahead of schedule.
Want results like these?
Find out where your operation's biggest opportunities are.
Start with an Assessment© USC Consulting Group 2026 | Mining & Metals. Representative industry image. Results are engagement-specific; sizing and forecast figures are labeled as such.

