Steel producing operation, Mining & Metals case study

Case study · Mining & Metals

Steel operation cuts scrap 30% for $45M in benefits

A steel operation needed lower scrap that would last. USC built a shared baseline, ran root-cause problem solving with the employees who run the process, and built the gains into daily reviews.

Results

$45M

in benefits

30%

reduction in scrap

The improvements were built with the people who run the process.

The situation

Scrap was too high, and improvements made on one shift were not carrying over to the next.

What the assessment found

  • No shared view of where scrap losses occurred
  • Fixes not sustained from shift to shift
  • Actions not owned within the operating system

How the work was done

Diagnose: one shared baseline

Built a shared baseline from data review and process observation.

Improve: test with employees

Ran root-cause problem solving with employees testing changes on the line.

30%

reduction in scrap

Sustain: own it daily

Added visual measures, daily reviews and named owners in the management operating system.

Lasting impact

Scrap fell 30%, with improvements built by the people who run the process and owned in daily reviews.