Large open-pit gold mine, North America, Mining & Metals case study

Case study · Mining & Metals

Gold producer raises ore throughput 24% with an operating system for mine and mill

An intermediate North American gold producer lost availability to weak mobile maintenance and an unmanaged mine-to-mill interface. USC built management operating systems for maintenance, mine production and the mine-to-mill interface.

Results

24%

increase in ore throughput over baseline

18%+

increase in fleet productivity

40%

reduction in maintenance backlog

Ore throughput also ran 10% over budget.

The situation

The open-pit operation was losing significant time to mobile equipment downtime, and planned and actual work diverged without explanation.

What the assessment found

  • Pre-service inspections rarely followed on mobile equipment
  • Mine-to-mill problems handled in unstructured meetings
  • Production and maintenance supervisors not communicating
  • No role-based targets for dispatchers and operators

How the work was done

Maintenance: structure the work

Built a maintenance and mine production management operating system (MOS) with scheduling, work assignment, follow-up and reporting, and trained users on the new disciplines.

40%

reduction in maintenance backlog

Mine-to-mill: manage the interface

Extended the same MOS to the mine-to-mill interface and process plant, with structured problem solving and shift-by-shift coaching.

24%

increase in ore throughput over baseline

Operations: plan every shift

Used the mine plan to build optimized daily and shift schedules, improved cross-department communication and sped parts from warehouse to down equipment.

18%+

increase in fleet productivity

People: set role-based targets

Reviewed and revised performance targets with executives and operational leaders, and rolled out tools to build individual and team skills.

Lasting impact

Changes in the field translated directly to the financial statements: more ore processed than baseline and budget, a smaller maintenance backlog and a more productive fleet.