1Challenge
A disconnected floor plan forced long material travel, fabrication was not linked to the main line, and assemblers kept leaving the line to fetch parts.
2Approach
- Quantified waste in each work cell and calculated true capacity through floor observation
- Created a new floor plan, consolidated two shifts into one and added short interval control
- Introduced kanban so parts were always at the line
3Results
20.5%
Throughput increase (136 to 164/day)
8.68→7.12%
Labor to sales, unit coolers
91→115%
Efficiency, unit coolers
The approach was then extended across the rest of the plant.