1Challenge
Production had grown from one or two aircraft a year to 18, with plans for 24. Contracts still reflected start-up volumes, while a large sales backlog gave the client new leverage.
2Approach
- Told the client's growth story openly, including its pain points with current agreements
- Used predictive models and analytics to show how each scenario affected BOM cost and supplier revenue
- Addressed where the client created friction for suppliers, since recertification makes switching parts costly
3Results
>$200K
Annual reduction in bill of materials
2
Critical supply agreements restructured
18/yr
Production level the new terms reflect
Win-win pricing, process and relationships rather than a supplier change.
Want results like these?
Find out where your operation's biggest opportunities are.
Start with an Assessment© USC Consulting Group 2026 | Aerospace & Manufacturing. Representative industry image. Results are engagement-specific; sizing and forecast figures are labeled as such.