1Challenge
Redesign manufacturing, assembly and management systems to fit one facility instead of two (9,300 m² and 4,700 m²). Objective: improve productivity, shorten cycle time and improve profitability.
2Approach
- Observed design, manufacturing and assembly across both buildings to find root causes and size the opportunity
- Redesigned material flows, staging and processes with proprietary simulation software
- Engaged all personnel, including the unionized workforce, from day one
3Results
>2.0:1
ROI, as measured by the client's finance team
2 → 1
Buildings consolidated into one facility
Zero
Disruption to ongoing operations
Completed over a year ago; the client remains very satisfied with the results.